Set a Comment Code for a Plan Task

To set a comment code for a Plan Task:

  1. Click Project in the Navigation pane.

  2. Click Plans for a project.

  3. Click Tasks for a plan.

  4. Click Vertical View for a task.

  5. Click Late Comment.

    NOTE: The Late Comment icon is disabled when the schedule status for a Plan Task or Work List Item is not late (i.e., its schedule status is on time (green) or behind (yellow)). The Late Comment icon is only available when a Plan Task or Work List item’s schedule status is late (red).

    NOTE: If no records exist, the page displays in add mode. Otherwise, click Add.

    View the field descriptions for the Item Comment Code page

  6. Select a code from LATE COMMENT CODE ID list box.

    NOTE: Comment codes are managed on the Comment Codes page.

  7. Enter a comment about the late task in COMMENT field, if necessary.

  8. Click Save.