Required Columns for Import into dspTrack™
To be imported into dspTrack™, the following columns are required in the spreadsheet or project file:
-
ID
-
Active
NOTE: dspTrack™ will only import tasks that are marked as Active in MicroSoft Project.
-
Task Mode
NOTE: Auto Scheduled is the only valid value in this column.
-
Name
NOTE: This value in this column displays in the NAME column on the PlanTask page after the file is imported.
-
Start Date
NOTE: This date corresponds to the Planned Start Date in dspTrack™.
-
Finish Date
NOTE: This date corresponds to the Planned Finish Date in dspTrack™.
-
Predecessors
NOTE: This column displays the ID of the predecessor task which is displayed on the PlanTask Dependency page after the file is imported.
-
Summary
NOTE: dspTrack™ does not import Summary tasks, so this column will always display No.
-
Critical
NOTE: This information displays on the Task’s Vertical View on the Additional Information tab after the file is imported.
-
Milestone
NOTE: This information displays on the Task’s Vertical View on the Additional Information tab.
-
Notes
NOTE: The data in this column displays on the PlanTask page’s Vertical View on the General tab, in the Description field after the file is imported.
-
Actual Start
NOTE: If the Actual Start date for a task to be imported is after the current date, the import will fail. If the file being imported into dspTrack™ is an Excel file, the Actual Start Date must be updated to a date equal to or earlier than the current date in the Excel file. If the file being imported into dspTrack™ is a Microsoft Project file, the Actual Start Date must be updated to a date equal to or earlier than the current date in Microsoft Project. After correcting the Actual Start Date, import the file again.
-
Actual Finish
NOTE: When importing a Microsoft Project file (.mpp), the Duration and Unit of Measure (UOM) fields are also imported for each plan task. When importing an Excel spreadsheet (.xlsx), if the Duration and Unit of Measure (UOM) fields are included, they will be imported as well. The Duration and UOM fields are also exported.
NOTE: If a project is imported into dspTrack™, and the slack value is in the form of a percent in Microsoft Project, that value will be displayed as number of days in the Slack and Slack UOM fields on the Plan Task Dependency page.
-
Duration
NOTE: This number, along with the Unit of Measure (UOM), determines how long the task should take to complete. This number can be a decimal and is used in schedule status calculations and on reports.
NOTE: The import will fail if the Duration field is 0 for any tasks in the project.
-
UOM
NOTE: This field, along with the Duration field, determines how long the task should take to complete and is used in Schedule Status calculations and on reports. Values are Days, Hours, Minutes, Months and Weeks.
Was this article helpful?
Sorry about that.
Why wasn't this helpful? (check all that apply)
Thanks for your feedback.
Want to tell us more?
Send an email to our authors to leave your feedback.
Great!
Thanks for your feedback.