Finish to Start

This dependency type dictates that work on the predecessor task must be finished before work on the dependent task can start.

A user clicks Next Action on the Work List to move the predecessor Plan Task from In Progress status to Completed status. The dependent task status moves from Waiting on Dependency to Ready status and work on the dependent task can begin.

When setting a Finish to Start dependency type, the planned finish date for the predecessor task must not be a later date than the planned start date for the dependent task. If the dates are not set correctly, an error message displays when saving the dependency on the Plan Task Dependency page.