Finish to Finish

This dependency type dictates that work on the predecessor task must be finished before work on the dependent task can be finished.

A user clicks Next Action on the Work List to move the predecessor Plan Task from In Progress to Completed status. Work on the dependent task may have already begun but cannot move from In Progress to Completed status until the predecessor task is in Completed status.

When setting a Finish to Finish dependency type, the planned finish date for the predecessor task must be earlier than the planned finish date of the dependent task. If the dates are not set correctly, an error message displays when saving the dependency on the Plan Task Dependency page.