Finish Work on a Work List Item or Plan Task

A user can mark an item as finished on the Work List, even if that item is late. Once an item is finished, it no longer displays on the Work List. Plan Tasks in a Completed status display on thePlan Taskpage and Work List Detail page. Work List Items in a Completed status display on theWork List Detailpage only.

NOTE: A user may be required to add a comment to  a Plan Task or Work List Item  that is late to finish it. Refer to Set Comment Requirements for Tasks for more information.

NOTE: Work on a task cannot finish if the task is in a status of Waiting on Dependency. In this case, if a user clicks Next Action on the Work List, the task(s) and dependency/dependencies preventing the task from finishing display. Work List Items cannot have dependencies, so will never be in the Waiting on Dependency status.

To finish a Plan Task or Work List Item:

  1. Click the blue tab on the Quick Panel to access the Work List.
  2. Click the Next Action button for the Plan Task or Work List Item with a STATUS of In Progress.

dspTrack™ removes the item from the Work List and updates the Actual Finish Date for the item.

Refer to Task Status for more information.